Monday, June 22, 2009

Buff Stuff

Last week my husband got the second half of the roof sheathed. The next step was to cover the entire roof in black, roofing felt. This took two of us, so I helped. It was really scary up there at first, but we got used to it. I like this photo because I look all buff and stuff. : )



It was hard to photograph this part because neither of us felt ok about taking the expensive camera up the ladder. So here's the view from below.



Next we'll cover the roof with metal. Apparently metal is much better for energy savings than shingles, but also more expensive.

Thursday, May 21, 2009

More Dads than you can shake a stick at

Here is a shot of all the trusses up and the framing for the roof completely finished. Whew!



Next, David's dad came over to help with the sheathing. We are VERY lucky to have such handy, generous parents in our lives - thank you guys!!! The sheathing is basically 4'x8' sheets of OSB, which is like plywood but different (as much as this girl got). Wayne had to heft it up to this little platform, climb up, then lift it up to David, perched on the roof.



Here's a close-up. I didn't want to climb the ladder with the camera, so it's from below.



Here's David up top with the nail gun:

And a final picture with much of one half done.

Wednesday, May 20, 2009

Trusses shmusses

So, after finishing the framing for the walls, squaring them, and putting the top plates on ... top, we had the trusses delivered (below).



My parents were here for a couple of days this weekend and my dad helped my husband put up ALL the trusses while my mom and I and Jacob hung out and went to thrift stores. : ) They started by putting the first one up on top of the 9ft walls, upside down.



Then they turned it over and fixed it in place. That's my dad (below).




Here's the view from my end of the building.



Here they are putting up the second truss:



They had a whole system going.



Here's my dad securing the third one.




Like I said they got them all up ... I post more pictures later.

Sunday, April 26, 2009

New recruits

My parents were kind enough to come down this weekend and help us out with our garage/studio. It mostly consisted of my dad helping to frame and my mom watching Jacob while I slept. : ) Thanks guys!!! This is my dad...



While I've been out of commission these last few days (due to poison oak) David has been putting up more sections of wall every night when he gets home from work (bless him). Today the big task was to construct and raise the heavy section for the garage door (below).



Here we are leveraging the wall over the bolts that are stuck in the cement.



And here my dad is putting in the last few screws that are temporarily, along with braces everywhere, holding it all up and together.



Next we'll be putting the rest of the wall sections up and then (the hard part) getting the trusses up for the roof.

Monday, April 20, 2009

First Wall (section) Up!

Well, this may not look very impressive, but it was HARD! When they poured the slab they put in some bolts along the edges that stick out a couple of inches (you can see a couple in the photo on the front part of the slab, to the right). We had to drill holes for these to fit in, along the bottom of this wall section, in exactly the right spots, and then lift all 16 feet (9 ft high) of it into place so the bolts fit into the holes. It took some manouvering, but David and I did it by ourselves. Only to realize we'd forgotten the plastic stuff that goes underneath. So we had to take it down and do it all over again. But it's up and steady and man are we proud of ourselves! On to the next section ...

Sunday, April 19, 2009

Slow going

My husband is a perfectionist, so of course this is going slower than we thought. I don't mind. I've been waiting this long to have my dream studio ... I can wait a little longer. It'll be the straightest, strongest, longest lasting studio on the block, you can bet! Besides, I'm getting used to the half a bedroom I'm in, and did I tell you ... my office is in the bathroom. : ) I'll take a picture of it later and post it here. It's pretty cute - kinda like this guy:

Saturday, April 18, 2009

First Load Delivered

Today this big ol' truck drove into our yard and unloaded all the wood we'll need to get started with the wall framing. We are going with McCoy's because of the FABULOUS service!



Because it's been raining a lot the last few days we put most of the wood on the slab so it doesn't get moldy on the ground. We're going to get buff fast from lifting all this wood!



We "stickered" this stack (below), which basically means we spaced it out so it'll get dry faster.



Below is Jacob showing me exactly how to work the measuring tape.



I kept asking if there was anything I could do and David kept saying "umm, not right now," so while I went inside and painted David laid out the first section of wall. We are going to do each 40' side in 3 sections so it's not too heavy to lift.



Here it is with one window framed in.



And here's Jacob again directing the project from his perch on the stickered wood pile.


More tomorrow...